Thursday, May 10, 2012

12th Green Cart Path Reconstruction

Removal of the old asphalt
 Today we started to replace the cart path  from left of the 12th green to the 13th tee complex. The old path has several cracks and areas that were lifted because of tree roots. The old asphalt was removed and the path was widened from 6 feet to 8 feet for easier equipment access. A six inch crushed gravel base was added and compacted. The new path will be paved early next week. After paving the sides of the path will be put back to grade with top soil and sodded.
Removal of an old tree stump on the edge of the old path
The sides of the path will have soil and sod added to give the project a finished look.