Wednesday, August 21, 2013

Fall aericifation & Master Plan construction






 The fall aerification schedule;
Greens and Tees- Sept. 3,4,5,6. The course will be closed Sept. 3rd
Fairway aerification will start on Sept 9,10,11,12,13,16. The course is closed on Sept 9th
 The Master Plan construction will start on September 9th. Holes 14,15, and 16 including the rebuild of the 14th green will be the first work completed. The 14th hole will be closed for the season once the work starts and the short game facility will be converted to a par three for the fall.

Saturday, July 20, 2013

Work Schedule for the week of July 22nd

In addition to the normal cutting schedules, the following work is scheduled for this week:
Calcium treatment to the club courts.
Solid tine greens venting on Monday.
Summer patch fungicide application to all our greens on Monday.
Preventative fungicide application on tees.
Post emerge treatment of crabgrass in some rough areas.
Continuation of prep work for our Master Plan work scheduled for September.

Saturday, June 22, 2013

Turf Twister

What is wrong with the turf??

This picture is of a small section of turf on our putting green where the bent grass has been severely injured, but the Poa is surviving. Any guess to what caused this injury??


Answer: During the putting contest on Member Guest weekend someone spilled an Adult beverage on the putting green. The alcohol in the drink injured the bent grass but the poa remains healthy. Goes to prove Poa can hold it's booze better than bent!

Friday, June 14, 2013

Mother Nature Wins

12th green cup filled with water
 Another 1.8 inches of rain fell last night giving us a total of almost 12 inches of rain in the last seven days. When the golf and grounds crew arrived at 5:30 AM this morning to start our prep for today's tournament almost every fairway had ponds of standing water on them along with several cups on the greens filled with water. There are also several bunkers that have water in them. Most of the rain fell between 1:30 AM and 5 AM.
Our plan of action is pump and rake the bunkers immediately. Greens will be cut and rolled and pin placements will be set starting at 10 AM .
All the work will be completed before the 1 PM shotgun start. We could use some of those 130 volunteers that the USGA has at the Open this week. Our staff of 20 will get it done!!!
Going to be a slow track today
New water hazard on 4 fairway


Thursday, June 13, 2013

Final Member Guest Prep

Greens rolling
 The final prep for the Silver Spring 2013 Member Guest Tournament is almost completed. Greens have been cut and rolled; fairways, tees, collars and approaches were also mowed this morning. A complete bunker rake will also be completed. The crew is also busy checking the course for any debris from last night's winds and a final clipping cleanup in the rough and perimeters/walkways will complete our prep work. Now if only Mother Nature cooperates and keeps the predicted heavy rains away we will be ready to have a great three days
Follow the straight lines to the green



Friday, May 17, 2013

Golf Archiect's visit

Roger, Peter, and Dave
 Yesterday the design team from Rulewich and Fleury Golf  Design spent the day with Green Chair Peter Morrice and Property Manager Peter Rappoccio, reviewing the Master Plan work scheduled to start in September. Holes 2, 3, 14 , 15 and 16 are scheduled to be reworked this fall. The emphasis of the work scheduled is to level and expand our teeing areas giving the membership more options to play from when they are out enjoying their course. Construction of additional tees will also be part of the plan as well as a reconstruction of our fairway and green side bunkers. Drainage of some fairway areas and tree work will also be part of the plan.
The Master Plan was originally approved by the Board in June of 2004. To date 6 holes plus the short game facility and the new putting green have been completed.
Peter Morrice with Roger and Dave

Tuesday, April 30, 2013

Dry- Ject Greens Tomorrow May 1st

Sand Injection process
 Tomorrow May 1st a Dry-ject aerification is scheduled for all the greens. Dry-ject aerification is a process by which sand is injected into the growing median at high pressure. The process leaves a column of sand below the putting surface which help relieve compaction in the soil and provide a channel for nutrients, water and root growth.
After the injection process, the greens are brushed, rolled and are ready for play.
The putting surface after injection