We are nearing completion of our Master Plan project for 2013. As of November 1st the work remainig consists of draining of the green side bunkers on 2; Sod installation of the forward tees on 2 ,8 and the three back tees on 3; Shaping of the forward tee on 3; shaping of the green bunkers on 3; construction of the fairway bunker on 2 repairing and sod installation on all the construction roads created by the project.
We estimate another two weeks of work.
|
New forward tee on 14 |
|
Installing fill to build the back tee on 3 |
|
Fill from the old football field at Joel Barlow High becomes the new tees on 3 |